1.1 rock particles prior to installation, the first reference to the packing list to check parts are complete and damage. 1.2 reference to the rock particles, machine installation drawings to install the chassis which support must be horizontally mounted on the foundation, the basis should have sufficient stiffness and strength to support the shaker all the dynamic load and static load. 1.3 can make use of the screen box trunnion lifting screen, not directly linked to the exciter on the lifting of the entire sieve. 1.4 installation screen machine, make sure to maintain a minimum 75mm gap between the screen box and hopper, trough a class of non-moving parts. 1.5 rock particles after installation, around the screen surface level, otherwise, the spring seat and bearing pad of thin iron plates to be adjusted. 1.6 The spring must be in a vertical state, the spring fixator in the ear axis of the screen box. 1.7 shaker drive direction as, standing on the feed side, the face of the material flow direction, and observe the motor position, the left hand side to left to drive, right hand side for the right to drive. The shaker symmetrical design, both sides pulley. Replace the motor position to drive the direction of change around. 1.8 to ensure that the V-belt tension the full amount of the adjustment of the two pulley face is adjusted in a plane. 1.9 test before hand (or other method) rotating exciter. Flexible rotation, no jamming phenomenon, before starting the machine. 1.10 installation adjustment is completed, the equipment should be carried out not less than two hours no load test run, to smooth operation, no abnormal noise bearing maximum temperature does not exceed 75 ℃. Rock particles, water for injection wetting a cotton ball to wipe machine hopper area of 25 cm2,. Wipe cotton ball three times with water for injection, extraction, the extract is diluted in water for injection to 50ml. Visual inspection and HPLC examination. |